TSX - SWY LAST: 0.37 -0.01 -1.33% Vol: 162,788 August 17, 2018

Project Overview

The 100% owned Renard Mine, Stornoway’s flagship asset, is located approximately 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau in the James Bay region of north-central Québec. Construction began on July 10, 2014, following the completion of a C$946 million project financing transaction, the largest ever for a publicly listed diamond company. Now completed, the mine is the first diamond mine in Québec, and one of only six in Canada, employing approximately 500 people. The project benefits from a large and growing resource, good mining conditions, strong social acceptance, a modest environmental footprint, and the development of direct-to-mine road infrastructure.

Now in commercial production, the mine is expected to produce an average of 1.6 million carats per year over an initial 14-year mine life, representing approximately 1% of global supply. First ore was delivered to the plant approximately 10 weeks ahead of schedule on July 15, 2016. Commercial production was declared on January 1, 2017.

In an era of steadily growing diamond demand and decreasing supply, Renard is one of the best diamond mines in the world today.

Renard’s Social Licence

The Renard Project was constructed under the terms of the March 2012 Mecheshoo Agreement between Stornoway and the Cree Nation of Mistissini, the Grand Council of the Crees (Eeyou Istchee), the Cree Regional Authority, and the terms of the July 2012 Partnership Agreements with the communities of Chibougamau and Chapais.

The Mecheshoo Agreement provides training, employment and business opportunities for Crees during project construction, operation and closure, as well as setting out social, cultural and environmental principles under which the mine will be managed and respected. The Mecheshoo Agreement also includes a mechanism by which the Cree parties will financially benefit from the success of the project on a long-term basis, consistent with the mining industry’s best practices for engagement with First Nations communities.

All major permits required for the construction period were obtained. The Renard Diamond Project Mining Lease was issued by the Québec Ministère des Ressources naturelles in October 2012 and the Québec Certificate of Authorization was issued by the Ministère du Développement durable, de l’Environnement, de la Faune et des Parcs (“MDDEFP”) in December 2012. The Company received a positive Federal Environmental Assessment decision in July 2013.

Renard and the Plan Nord

An important aspect of the Renard Mine was the Route 167 extension, allowing all-season access to Renard by way of the Chibougamau and Mistissini communities and which has been constructed under the auspices of Québec’s Plan Nord. Construction began in February of 2012, and was undertaken in four segments, “A” to “D”. Under the terms of a November 2012 Framework Agreement between Stornoway and the Government of Québec, Québec completed the first 143 km of road (segments “A” and “B”) as a 70 km/hr two-lane gravel highway and Stornoway undertook the construction of a 50 km/hr single-lane mining road over the remaining 97 km (segments “C” and “D”) as the “Renard Mine Road”. The cost of the Renard Mine Road was initially estimated at $77 million, including a 15% contingency. Under the terms of the December 2012 Financing Agreement between Stornoway and Québec, Stornoway’s road costs have been funded through a credit facility provided to Stornoway bearing a 3.35% interest rate, amortized over a 15-year period. All four segments of the road were connected in September 2013, two months ahead of schedule and 10% below budget. A first for diamond mines operating in Canada, year-round road access will allow Renard to be operated with significantly reduced costs and operating risk.

Renard Mine Construction

The Renard Diamond Project was constructed under an Engineering, Procurement and Construction Management (“EPCM”) agreement between Stornoway and SNC-Lavalin Inc. SNC-Lavalin provided EPCM services for on-site utilities such as the liquefied natural gas power plant, the processing plant building, service buildings, water treatment facilities, and on-site infrastructure. The agreement with SNC-Lavalin contemplated sub-contracted services to be provided by AMEC Americas Ltd. and DRA Americas Inc. for certain specialized engineering and field support services relating to the project’s diamond processing plant and diamond recovery circuits. The total capital cost of site facilities and infrastructure within the scope of the EPCM contract was estimated at approximately C$425 million. Construction under the balance of the project’s C$811 million capital cost was managed by Stornoway’s corporate team based in Longueuil, Québec. In February 2016, management re-baselined the cost and schedule of the project, resulting in a $36 million decrease in capital cost for the project to $775 million and a 5 month improvement in the scheduled date of commercial production to December 31, 2016.

RENARD PROJECT PHOTO GALLERY

 

INVESTOR EVENTS

Related Press Releases

August 14, 2018 Stornoway Reports FY2018 Second Quarter Financial Results
LONGUEUIL, Quebec, Aug. 14, 2018 (GLOBE NEWSWIRE) - Stornoway Diamond Corporation (TSX:SWY; the “Corporation” or “Stornoway”) is pleased to report financial and operating results for the quarter ended June 30, 2018. QUARTER ENDED JUNE 30, 2018 HIGHLIGHTS: (All quoted figures in CAD$, unless otherwise noted) For the three months ended June 30, 2018, Stornoway reported a net loss of $35.9 million ($0.04 per share on a basic and fully diluted basis). Adjusted net loss1 for the quarter was $31.3 million. During the quarter, two tender sales totalling 201,283 carats were completed for gross proceeds2 of $28.6 million3 at an average price of US$109 per carat ($142 per carat3). Revenue recognized was $56.9 million, derived from the sale of 328,899 carats of run of mine production in three tender sales at an average achieved price1 of US$115 per carat ($147 per carat1,[4]), and the sale of 41,979 carats of incidental production in one out of tender contract sale at an average price of US$19...
More
August 08, 2018  Stornoway Announces Second Quarter Earnings Release Date
LONGUEUIL, Quebec, Aug. 08, 2018 (GLOBE NEWSWIRE) - Stornoway Diamond Corporation (TSX:SWY) (the “Corporation” or “Stornoway”) expects to release its Second Quarter 2018 results prior to market open on August 14, 2018 and will host a conference call for analysts and investors on August 14, 2018 at 11:00 a.m. EDT. A webcast of the conference call will also be available. The details for the call and the webcast are: Toll Free: (844) 215-3287 International: (209) 905-5939 Conference ID: 9348237 https://edge.media-server.com/m6/p/um4rmfby Replays of the second quarter earnings conference call will be made available on Stornoway’s website. ABOUT THE RENARD DIAMOND MINE The Renard Diamond Mine is Quebec’s first producing diamond mine and Canada’s sixth. It is located approximately 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau in the James Bay region of north-central Québec. Construction on the project commenced on July 10, 2014, and commercial production...
More
July 06, 2018 Stornoway Reports Second Quarter 2018 Production And Sales Results
LONGUEUIL, Quebec, July 06, 2018 (GLOBE NEWSWIRE) - Stornoway Diamond Corporation (TSX:SWY) (the “Corporation” or “Stornoway”) is pleased to provide production and sales results at the Renard Diamond Mine for the second quarter ended June 30, 2018.  Highlights are as follows: (All quoted figures in CAD$ unless otherwise noted) 201,283 carats sold in two tender sales for gross proceeds1 of $28.6 million2 at an average price of US$109 per carat ($142 per carat2). Second quarter diamond production was 223,351 carats produced from the processing of 562,060 tonnes of ore at an average grade of 40 carats per hundred tonnes (“cpht”). Grade and carat recoveries during the quarter reflect the processing of lower grade production ore and ore stockpiles as the Renard Mine transitions from open pit to underground mining. Mining in the Renard 3 open pit concluded in April. Ramp up of the underground mine production progressed steadily during the quarter, with mined underground tonnes...
More